File #: 23-533   
Type: Resolution Status: Passed
File created: 11/9/2023 In control: County Board
On agenda: 12/12/2023 Final action: 12/12/2023
Title: APPROVING AN INTERGOVERNMENTAL AGREEMENT WITH THE STATE OF ILLINOIS FOR PHASE III CONSTRUCTION FOR LONGMEADOW PARKWAY CORRIDOR SECTION C-2B FROM EAST OF SANDBLOOM ROAD TO BOLZ ROAD CONNECTOR, KANE COUNTY SECTION NO. 21-00215-29-CH
Attachments: 1. Exec. Sum., 2. , 3.
title
APPROVING AN INTERGOVERNMENTAL AGREEMENT WITH THE STATE OF ILLINOIS FOR PHASE III CONSTRUCTION FOR LONGMEADOW PARKWAY CORRIDOR SECTION C-2B FROM EAST OF SANDBLOOM ROAD TO BOLZ ROAD CONNECTOR, KANE COUNTY SECTION NO. 21-00215-29-CH
body
WHEREAS, the Illinois Constitution of 1970, Article VII, Section 10 and the Illinois Compiled Statutes, (5 ILCS 220/1, et seq.) authorizes the County of Kane (County) and the State of Illinois (State) to cooperate in the performance of their respective duties and responsibilities by contract and other agreements; and

WHEREAS, the County and the State (through its Illinois Department of Transportation) desire to cooperate among themselves to accomplish the Longmeadow Parkway Corridor Section C2-B Project (Kane County Section No. 21-00215-29-CH), (hereinafter referred to as the "Improvement"); and

WHEREAS, the County and the State desire to undertake Phase III Construction Engineering for the Improvement at an estimated cost of Two Million Six Hundred Sixty Nine Thousand One Hundred Forty Six and 85/100 Dollars ($2,669,146.85); and

WHEREAS, the Improvement is deemed by the County and the State to be of immediate benefit to the residents of the County of Kane and the State of Illinois in that it shall facilitate the efficient movement of traffic and provide for the safety of the motoring public; and

WHEREAS, the County and the State have determined a mutually satisfactory allocation of responsibilities and costs for said Improvement as set forth in an intergovernmental agreement with the State (a copy of which is on file with the Kane County Clerk's Office), with the County's share of the Phase III Construction Engineering costs estimated to be One Million One Hundred Sixty Nine Thousand One Hundred Forty Six and 85/100 Dollars ($1,169,146.85).











NOW, THEREFORE, BE IT RESOLVED by the Kane C...