File #: TMP-26-178   
Type: Resolution Status: Reported to County Board
File created: 2/2/2026 In control: County Board
On agenda: 3/10/2026 Final action:
Title: APPROVING A RELOCATION COMMITMENT AGREEMENT WITH COMMONWEALTH EDISON COMPANY FOR THE RELOCATION OF FACILITIES FOR THE RANDALL ROAD AT HOPPS ROAD INTERSECTION IMPROVEMENT AND GRADE SEPARATION PROJECT, KANE COUNTY SECTION NO. 19-00511-00-CH
Attachments: 1. Exec. Sum., 2. , 3.
title
APPROVING A RELOCATION COMMITMENT AGREEMENT WITH COMMONWEALTH EDISON COMPANY FOR THE RELOCATION OF FACILITIES FOR THE RANDALL ROAD AT HOPPS ROAD INTERSECTION IMPROVEMENT AND GRADE SEPARATION PROJECT, KANE COUNTY SECTION NO. 19-00511-00-CH
body
WHEREAS, Commonwealth Edison Company ("ComEd") has existing utility easements within the limits of the Kane County Highway No. 34 (Randall Road) and Hopps Road Intersection Improvement and Grade Separation Project (the "Improvement Project"); and

WHEREAS, several ComEd transmission utility towers are currently standing within said easements and must be relocated in order to complete the Improvement Project; and

WHEREAS, the County of Kane is responsible for the relocation cost of the ComEd facilities in ComEd's easements along part of the Improvement Project pursuant to the Illinois Public Utilities Act (220 ILCS 5/1-101, et seq.); and

WHEREAS, pursuant to Kane County Resolution No. 25-136, ComEd and Kane County entered into a Relocation Commitment Agreement to facilitate the relocation of the existing transmission utility towers which consists of three (3) phases of work: 1 (Scoping Engineering), Phase 2 (Detailed Engineering) and Phase 3 (Construction) and appropriated One Hundred Thousand Dollars ($100,000.00); and

WHEREAS, pursuant to Kane County Resolution No. 25-426, ComEd and Kane County entered into a Relocation Commitment Agreement to facilitate the relocation of the existing transmission utility towers, which consists of three (3) phases of work: Phase 1 (Scoping Engineering), Phase 2 (Detailed Engineering) and Phase 3 (Construction) and appropriated One Million Dollars ($1,000,000.00); and

WHEREAS, ComEd requires an additional appropriation of Two Million Four Hundred Thousand Dollars ($2,400,000.00) to maintain the expedited schedule of the Project.

NOW, THEREFORE, BE IT RESOLVED by the Kane County Board that the County o...

Click here for full text