Resolution Approving a Bid for Construction of Phase II Site Improvements at Brunner Family Forest Preserve
body
WHEREAS, it is deemed necessary and desirable for the Commissioners of the Forest Preserve District of Kane County, Kane County, Illinois, to authorize bids for trail restoration and drainage improvements at the Brunner Family Forest Preserve in Dundee; and
WHEREAS, the District conducted a formal bid process for the improvements; and
WHEREAS, Obsidian Asphalt Paving, Inc. was the qualified, lowest bidder, with a base bid of $459,706.71. Additionally, $15,293.29 shall be set aside as contingency to cover any unanticipated additional costs, for a total contract amount not to exceed $475,000.00.
NOW, THEREFORE, BE IT RESOLVED by the Board of Commissioners of the Forest Preserve District of Kane County, Illinois, that the qualified, lowest bid from Obsidian Asphalt Paving, Inc. for Phase II Site Improvements at Brunner Family Forest Preserve for $459,706.71, plus a contingency of $15,293.29 for a total contract amount not to exceed Four hundred and seventy-five thousand dollars ($475,000.00) be, and hereby is accepted and approved.
APPROVED AND PASSED on this 8th day of July 2025.
___________________________ ____________________________
Bill Lenert Mohammad Iqbal
President, Kane Forest Preserve Secretary, Kane Forest Preserve