File #: TMP-24-2374   
Type: Zoning Petition Status: Passed
File created: 5/15/2024 In control: County Board
On agenda: 6/11/2024 Final action: 6/11/2024
Title: Petition # 4631 Petitioner: Michael Vondra (TPE IL KN309, LLC)
Attachments: 1. Exec. Sum., 2. , 3. , 4. , 5.
body
Petition #: 4631
Committee Flow: Development Committee
Contact: Keith Berkhout
Petitioner: Michael Vondra (TPE IL KN309, LLC)
Location: 2S512 Lorang Road (10-25-400-006), Kaneville Township
Proposed: Special Use request in the F-Farming District for a solar facility
2040 Plan: Agricultural/Resource Managmeent
Objectors: None
Recommendations:
Regional Planning Comm.: N/A
Zoning Board: Approval with the recommended stipulations:

1. Water Resources will require a stormwater permit for this development.
2. An Engineer's report will be required. Should the site introduce more than 25,000 square feet of impervious area or more than 3 acres of disturbance, stormwater detention will be required. This impervious area is calculated cumulatively since 2002 for a site as per the Stormwater Ordinance. The Engineer's report must demonstrate that the peak flow for the site with the proposed development is not increased, stormwater detention may be required for the development to ensure this. Any required Stormwater Detention Management will require a viable outfall and may require off-site work.
3. Should the site introduce more than 5,000 square feet of impervious, a BMP will be required for all impervious surfaces.
4. A calculation for disconnected impervious area, created by the panels, will be required. A Best Management Practice will be required to encourage infiltration of runoff within the site.
5. A drain tile study will be required, including upstream and downstream tile systems that rely on the drain tiles within the site. Water Resources is looking for the protection of the tile system that is in place, including but not limited to replacement in kind and observation and cleanout structures.
6. Plantings within the development will not interfere with drain tiles. Planting plan should address the placement of vegetation and trees with long root systems that can interfere with tile systems and cause off site issues including surcharged drain tiles and blow outs...

Click here for full text