File #: 25-136   
Type: Resolution Status: Passed
File created: 3/7/2025 In control: County Board
On agenda: 4/8/2025 Final action: 4/8/2025
Title: APPROVING A $100,000.00 RELOCATION COMMITMENT AGREEMENT WITH COMMONWEALTH EDISON COMPANY FOR RELOCATION OF FACILITIES FOR THE RANDALL ROAD AT HOPPS ROAD INTERSECTION IMPROVEMENT, KANE COUNTY SECTION NO. 19-00511-00-CH
Attachments: 1. Exec. Sum., 2.
title
APPROVING A $100,000.00 RELOCATION COMMITMENT AGREEMENT WITH COMMONWEALTH EDISON COMPANY FOR RELOCATION OF FACILITIES FOR THE RANDALL ROAD AT HOPPS ROAD INTERSECTION IMPROVEMENT, KANE COUNTY SECTION NO. 19-00511-00-CH

body
WHEREAS, Commonwealth Edison Company (ComEd) has existing utility easements within the limits of Kane County Highway No. 34 (Randall Road) and Hopps Road Intersection Improvement Project (the "Improvement Project"); and

WHEREAS, several ComEd transmission utility towers are currently standing within said easements, and must be relocated in order to complete the Improvement Project; and

WHEREAS, the County of Kane is responsible for the relocation cost of the ComEd facilities in ComEd's easements along part of the Improvement Project pursuant to the Illinois Public Utilities Act (220 ILCS 5/1-101, et seq.); and

WHEREAS, ComEd and Kane County must enter into a Relocation Agreement to facilitate the relocation of the existing transmission utility towers, which consists of three (3) phases of work: Phase 1 (Scoping Engineering), Phase 2 (Detailed Engineering) and Phase 3 (Construction); and

WHEREAS, ComEd requires Kane County to provide a deposit of One Hundred Thousand Dollars ($100,000.00) for the estimated Phase 1 Scoping Engineering costs and execute a Relocation Commitment Agreement.

NOW, THEREFORE, BE IT RESOLVED by the Kane County Board that the County of Kane enter into a facilities relocation agreement with ComEd and further authorizes the Chairman thereof to execute a Relocation Commitment Agreement with the Commonwealth Edison Company for relocation of transmission utility towers from within the limits of the Randall Road at Hopps Road Intersection Improvement Project.

BE IT FURTHER RESOLVED that the Kane County Board hereby appropriates the not to exceed sum of One Hundred Thousand Dollars (100,000.00) from Transportation Sales Tax Fund #305, Lin...