Legislation Details

File #: TMP-26-1043   
Type: Resolution Status: Reported to County Board
File created: 8/7/2026 In control: KC Executive Committee
On agenda: 9/2/2026 Final action:
Title: APPROVING A CONTRACT FOR CONSTRUCTION WITH DUNNET BAY CONSTRUCTION COMPANY OF GLENDALE HEIGHTS, ILLINOIS FOR KIRK ROAD OVER UPRR BRIDGE REPLACEMENT, KANE COUNTY SECTION NO. 12-00192-04-BR
Attachments: 1. Exec. Sum., 2. , 3.

title

Approving a Contract for Construction with Dunnet Bay Construction Company of Glendale Heights, Illinois for Kirk Road over UPRR Bridge Replacement, Kane County Section No. 12-00192-04-BR

 

body

WHEREAS, bids have been solicited and received by the Illinois Department of Transportation (IDOT) for the work and/or construction described as:

 

KANE COUNTY SECTION NO. 12-00192-04-BR

KIRK ROAD OVER UPRR BRIDGE REPLACEMENT

(hereinafter the “Project”)

 

WHEREAS, the lowest responsible bidder for the Project is:

 

DUNNET BAY CONSTRUCTION COMPANY OF

GLENDALE HEIGHTS, ILLINOS

With a low bid of

$36,611,206.15

 

WHEREAS, pursuant to Kane County Resolution No. 26-282, Kane County previously entered into a Local Agency Agreement for Federal Participation in the Project utilizing Federal, State and County funds to pay for the construction costs thereof; and

 

WHEREAS, the Project is estimated to be funded in the amount of Twenty-Four Million Six Hundred Eight Thousand Dollars ($24,608,000.00) with Federal and State funds with the County’s share of the Project estimated to be Twelve Million Three Thousand Two Hundred Six and 15/100 Dollars ($12,003,206.15); and

 

WHEREAS, the County deems it prudent to include in its estimated Project cost a Twenty Percent (20%) contingency of the County’s share of the Project, amounting to Two Million Four Hundred Thousand Six Hundred Forty-One and 23/100 Dollars ($2,400,641.23).

 

NOW, THEREFORE, BE IT RESOLVED by the Kane County Board that the award of a contract by IDOT for the construction of the Project is hereby approved and there is hereby appropriated Four Million Dollars ($4,000,000.00) from the Motor Fuel Tax Fund #302, Line Item #73010 (Bridge Construction) and Ten Million Four Hundred Three Thousand Eight Hundred Forty-Seven and 38/100 Dollars ($10,403,847.38) from the Transportation Sales Tax Fund #305, Line Item #73010 (Bridge Construction) for a total of Fourteen Million Four Hundred Three Thousand Eight Hundred Forty-Seven and 38/100 Dollars ($14,403,847.38) to pay for the Project.

 

Line Item: 302.520.522.73010, 305.520.527.73010

Line Item Description: Bridge Construction

Was Personnel/Item/Service approved in original budget or a subsequent budget revision? Yes

Are funds currently available for this Personnel/Item/Service in the specific line item? Yes

If funds are not currently available in the specified line item, where are the funds available? N/A

 

Passed by the Kane County Board on September 8, 2026.

 

 

 ____________________________               ____________________________

John A. Cunningham, MBA, JD, JD               Corinne M. Pierog MA, MBA

Clerk, County Board                                       Chairman, County Board

Kane County, Illinois                                       Kane County, Illinois

 

Vote: